SLOPE SINKING AT THE “OKRUZHNAYA” STATION STARTED

Calendar
Subscribe news
February, 2020
Mo
Tu
We
Th
Fr
Sa
Su
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
1
27.01.2020

At the site № 17 on December 2, the tunneling of the second inclined tunnel of the “Okruzhnaya” station of the Lyublinsko-Dmitrovskaya metro line began. On January 27, 25 cast iron rings of 148 were mounted.

The tunneling is carried out by the employees of section № 1 of TO-6 under the leadership of Evgeny Korobov with the help of the TNU-3 tubing stacker.

A tunnel with a diameter of 8.5 meters will connect the “Okruzhnaya” station of the Lyublinsko-Dmitrovskaya line with the northern lobby.